Element 1
Takt time.
The available working time divided by customer demand.
Glossary
The current best known way to do a repetitive task, written down and followed by everyone who does it.
Element 1
The available working time divided by customer demand.
Element 2
The order of the operator’s steps, including walking, so the cycle fits within takt.
Element 3
The minimum number of parts inside the process for the work to flow without waiting.
A 7.5-hour shift has 27,000 seconds; for 450 rollers a shift, the takt time is 60 seconds.
One operator assembles conveyor idler rollers in a five-station U-shaped cell. The standard work sheet shows the layout and the path; the combination table shows the timing.
Standard work sheet
Standard work combination table
| Step | Work element | Manual | Auto | Walk | Time, 0 to 66 s |
|---|---|---|---|---|---|
| 1 | Unload the pressed tube, load a new tube and two bearings, start the press | 9 | 18 | 2 | |
| 2 | Fit the first retaining ring on a shaft | 10 | 2 | ||
| 3 | Insert the shaft into the pressed tube and fit the second ring | 14 | 2 | ||
| 4 | Spin-test the roller | 8 | 2 | ||
| 5 | Label the roller and place it on the outgoing rack | 3 | 2 | ||
| Total, in seconds | 44 | 18 | 10 | Cycle time 54 s, takt time 60 s |
| Criterion | Standard work | SOP | Work instruction |
|---|---|---|---|
| Focus | Sequence, timing and work in process of repetitive work, at takt | Who does what in a process, and when | How to do each step of one task |
| Written by | Team leaders and operators, with production engineering | Process owners and quality | Engineers, technical writers and experts |
| Changes when | Demand, the layout or the method improves | The process or the responsibilities change | The product, the tooling or the method changes |
| Usual form | Standard work sheet and combination table, posted at the cell | Controlled document | Step-by-step instruction with photos, drawings or 3D views |
Read more about standard operating procedures and work instructions.
TwinWorks
In TwinWorks, they open in a browser at the workstation from a link or a product QR code, with the 3D model showing each step.
Standard work, or standardized work, is the current best known way to do a repetitive task, written down and followed by everyone who does it. It comes from the Toyota Production System and rests on three elements: the takt time, the pace at which customers buy; the work sequence, the steps in the order that works best; and the standard work in process, the minimum number of parts that must wait between steps. It is the baseline that every improvement, or kaizen, starts from.
Takt time, the pace at which customers buy; the work sequence, the order of the operator’s steps; and the standard work in process, the minimum number of parts that must be in the process for it to run smoothly.
Standard work fixes the sequence, timing and work in process of a repetitive task against takt time. A work instruction explains how to do each step, with the tools, settings, key points and checks. Standard work relies on work instructions to train operators.
Takt time is the pace that demand requires: the available working time divided by the quantity customers need. Cycle time is how long the work actually takes. Standard work keeps the cycle time at or below the takt time.
Yes. Standard work and standardized work are two names for the same lean method, which comes from the Toyota Production System.
Use the free work instruction template to capture each step, its key points and its checks, ready to use at the workstation.